2024 Capital Improvement Projects & Programs
The City of West Chicago’s Public Works Department oversees the development and execution of the City’s Capital Improvement Projects and Programs. For more information about the City's Capital Improvement Projects and Programs, please contact Dave Shah, P.E., Assistant Director of Public Works, at (630) 293-2255, or dshah@westchicago.org.
To navigate to specific projects on this page, please use the navigation buttons, or follow this link to return to the Public Works webpage. The City has also provided a link to view the 2024 Capital Improvement Project map.
2024 Roadway Rehabilitation Project
Project Status
- Completed
Project Details
- Project Start Date: April 2024
- Substantial Completion: July 2024
- Project Advertisement: February 15, 2024
- Bid Opening: February 29, 2024
- Contract Amount: $940,368.23
- City Council Approval Date: March 18, 2024
- Awarded Contractor: Schroeder Asphalt Services, Inc
- Funding Source: Motor Fuel Tax
- Project Announcement: 2024 Roadway Rehabilitation Projects Scheduled through July
Project Location
- Diversey Parkway from Norris Avenue to IL-59
- Mulberry Drive from Diversey Parkway to Indianwood Lane
- Eagle Ridge Court off Mulberry Drive
- Indianwood Lane off Arapaho Drive
- Arapaho Drive from Indianwood Lane to Chippewa Lane
- Chippewa Lane from Arapaho Drive to Cherokee Drive
- Cherokee Drive from Indianwood Lane to Chippewa Lane
- Ancient Oaks Drive from IL-64
- Chalrestowne Drive from Kings Circle to Arbor Avenue
- Yale Street from W. National Street to W. Elmwood Avenue
- Elmwood Avenue from Yale Street to Fremont Street
- Grand Lake Boulevard from IL-59 to Ridgeland Avenue
View a map of the project location on the City's website.
Project Scope
The 2024 Roadway Rehabilitation Project includes resurfacing approximately 1.55 miles of various streets. The Project’s scope generally consists of the following:
- pavement milling;
- hot-mix asphalt (HMA) resurfacing;
- full-depth HMA pavement patching;
- intermittent concrete sidewalk, including, ADA curb ramps, intermittent combination concrete curb and gutter removal and replacement;
- storm and sanitary sewer repairs, including storm and sanitary structure replacement and adjustments;
- parkway restoration; and
- thermoplastic pavement markings.
Project Contact Information
- Project Related Questions/Accessibility Accommodations: Tomasz Tretowicz (217) 419-1709
- General Inquiries: Dave Shah (630) 293-2255
Conde Street Resurfacing Project
Project Status
- Substantially Complete
Project Details
- Project Start Date: May 2024
- Substantial Completion: August 2024
- Project Advertisement: August 18, 2023
- Bid Opening: September 22, 2023 (IDOT)
- Contract Amount: $679,998.50
- Award Date: October 23, 2024 (IDOT)
- Awarded Contractor: A Lamp Concrete Contractors, Inc.
- Funding Source: STP & Local
Project Location
- Conde Street from IL-59 (Neltnor Blvd) to Joliet Street
View a map of the project location on the City's website.
Project Scope
The Project consists of pavement milling and resurfacing, partial-depth pavement patching, intermittent curb and gutter replacement, ADA curb ramp upgrades, pavement markings, street lighting improvements, and parkway restoration.
Project Contact Information
- Project Related Questions/Accessibility Accommodations: Brandt Zentner (630) 918-4058
- General Inquiries: Dave Shah (630) 293-2255
2024 Sidewalk and Curb Maintenance Program
Project Status
- Completed
Project Details
- Project Start Date: July 2024
- Substantial Completion: October 2024
- Project Advertisement: March 5, 2025
- Bid Opening: March 26, 2024
- Contract Amount: $110,000.00
- City Council Approval Date: April 15, 2024
- Awarded Contractor: Strada Construction Co.
- Funding Source: Local
Project Location
- View a map of the project locations on the City's website.
Project Scope
- The project consists of intermittent removal and replacement of approximately 3,900 square feet of sidewalk and 250 linear feet of curb and gutter at various locations throughout the City. The Program also includes the construction of an aggregate base course for ground stabilization, inlet adjustments, detectable warning installation, tree root pruning, and restoration items, including hot-mix-asphalt and concrete driveway replacements, pavement patching, and sodding.
Project Contact Information
- Project Related Questions/Accessibility Accommodations: Tomasz Tretowicz (217) 419-1709
- General Inquiries: Dave Shah (630) 293-2255
Klein Road Culvert Replacement Project
Project Status
- Completed
Project Details
- Project Start Date: April 2024
- Substantial Completion: June 2024
- Project Advertisement: July 6, 2023
- Bid Opening: July 20, 2023
- Contract Amount: $622,932.62
- City Council Approval Date: August 21, 2023
- Awarded Contractor: Alliance Contractors, Inc.
- Founding Source: DuPage County Grant & Local
- Funding Source: STP & Local
- Project Announcement: Klein Road Closed through June Due to Construction
Project Location
- Klein Road 0.170 miles north of Meadowlark Drive
View a map of the project location on the City's website.
Project Scope
The Project’s scope includes the removal of the existing corrugated metal pipe culvert and two cast-in-place (CIP) junction chambers and replacing it with a single-cell, 6’ x 3’ precast concrete box culvert with a CIP end section, solider pile retaining wall and a precast concrete junction chamber, full depth hot-mix asphalt (HMA) pavement removal and reconstruction, HMA resurfacing, widening and placement of 8-foot HMA bike path to accommodate for future Wayne Township’s bike path project along Klein Road, HMA and aggregate shoulder construction, storm sewer improvements, temporary detour, thermoplastic pavement markings, fieldstone riprap installation, tree removals, native planting, landscaping, and other collateral work necessary to complete the project.
Project Contact Information
- Project Related Questions/Accessibility Accommodations: William Zbylut (331) 234-0736
- General Inquiries: Dave Shah (630) 293-2255
Harvester Road Reconstruction Project
Project Status
- Substantially Completed
Project Details
- Project Start Date: May 2024
- Substantial Completion: October 2024
- Project Advertisement: February 29, 2024
- Bid Opening: March 21, 2024
- Contract Amount: $3,819,800.57
- City Council Approval Date: April 15, 2024
- Awarded Contractor: Plote Construction, Inc.
- Funding Source: MFT, Local
Project Location
- Harvester Road between Powis Road and Hawthorne Lane
View a map of the project location on the City's website.
Project Scope
The Project includes full-depth reconstruction and widening of road pavement with 10” jointed Portland Cement Concrete (PCC) pavement, street light removal and replacement, new sidewalk construction, installation of ADA-compliant detectable warnings and curb ramps, driveway removal and replacement with curb & gutter, relocation of fire hydrants, miscellaneous storm sewer structure adjustments, reconstruction and replacement of spot sanitary sewer structures and pipes, and other miscellaneous work as denoted in the Project plans and specifications.
Project Contact Information
- Project Related Questions/Accessibility Accommodations: Jeff Andrzejewski (708) 846-8978
- General Inquiries: Dave Shah (630) 293-2255
2024 Pavement Preventative Maintenance Program
Project Status
- Completed
Project Details
- Project Start Date: May 2024
- Substantial Completion: June 2024
- Project Advertisement: N/A
- Bid Opening: N/A
- Contract Amount: $49,999.20
- City Council Approval Date: April 15, 2024
- Awarded Contractor: Corrective Asphalt Materials (CAM) LLC.
- Funding Source: Local
Project Location
- Stockberry Lane from Overbeck Lane to Lehman Drive
- Sophia Street from Washington Street to Turner Court
- McConnel Avenue from Sophia Street to Dead End
- Ingalton Avenue from Grand Lake Boulevard to James Avenue
- Elmwood Avenue from IL-59 to Ingalton Avenue
- Wendall Avenue from IL-59 to Ingalton Avenue
- Grand Lake Blvd from IL-59 to Ingalton Avenue
- National Street from Ingalton Avenue to Yale Street
- Bishop Street from IL-38 to Forest Avenue
- Augusta Avenue from Joliet Street to Bishop Street
View a map of the project location on the City's website.
Project Scope
- The project includes the spray application of Reclamite and the application of the lime screening on existing hot-mix-asphalt (HMA) pavement to rejuvenate the HMA pavement properties to prolong the life of the pavement. Furthermore, the project includes sweeping, and disposal of the aggregate by the contractor, and proper traffic control and protection.
Project Contact Information
- Project Related Questions/Accessibility Accommodations: Tomasz Tretowicz (217) 419-1709
- General Inquiries: Dave Shah (630) 293-2255